Custom – Premium build

Demo design – fictional business. Built by ProTrade Web Building. Projects, prices and reviews are examples.

Free roof survey
Chimney stack after repointing with new lead flashing

Project 03 · Otley

Chimney rebuild & leadwork

Top courses rebuilt, the stack repointed and new code 4 lead – three days from a chimney scaffold.

Work
Rebuild, repoint, lead
Access
Chimney scaffold
On site
3 days
Guarantee
Example: 10 yrs workmanship

01Before / After

Chimney stack after repointing with new lead flashing
Brick chimney stack with failing pointing and old flashing

02Scope

  • 01Chimney scaffold – no full house scaffold
  • 02Take down and rebuild top four courses
  • 03Rake out and repoint the stack
  • 04New pots and flaunching
  • 05Code 4 lead apron, soakers and back gutter

03Timeline

  1. Day 1

    Scaffold, take down top courses

  2. Day 2

    Rebuild, repoint, new pots and flaunching

  3. Day 3

    Leadwork, clean down, scaffold off

04Materials

Brick
Reclaimed to match
Mortar
Lime-based to match original
Lead
Code 4 apron and soakers
Pots
Buff clay, cowled